Category:
Water Treatment
Constructed:
May 2009 - April 2010
Project Value:
$4,500,000
Owner:
The Region of Peel
General Contractor:
Maple Reinders Constructors Ltd.
Forming contractor Form, place, finish concrete water retaining structures and pump facility(concrete supply by Others)
To quote GC Maple Reinders’ Project Manager, Adam Coombs:
Starting on June 7th, 2009, with 8150m3 of concrete in 250 separate pours, 780 tonnes of rebar, 14695572 liters of dewatering, 67 vertical feet from base of excavation to the roof. Despite… being held to 7 day wall stripping and 21 days for suspended slabs.
With special thanks to our formwork sub-contractor REIMAR Construction Corporation, and all our Division 2/3 Sub’s we have completed our last major roof pour today, and are on target to complete the membrane building expansion a full two months ahead of the original schedule.